Beersdalweg Ready for the Future: Sustainable with Great Results
Beersdalweg will reopen on Sunday, October 11. We have completed major maintenance on the pavement. The road connects the inner ring road to the highway. The work took 8 weeks. It went according to plan.

How did we work?
We used a new method. We reused the old road foundation on site. That saved us time. We also avoided 800 truck trips. That’s good for the environment.
Roadwork causes temporary inconvenience. But once it’s done, you’ll have a road that will last for years to come.
Due to heavy rain, we were unable to apply the final road markings on time. That is why the road did not open until after the weekend. We will finish the final markings after rush hour. Now this important transportation route is back in good condition for years to come.